فارسی
Home
About Us
History
Board of Directors
Management systems
Key Personnel
Join and consents
Membership of the Association
Specialized machinery
Excavation, piling and pile driving
Underground piping
Stone columns, Nailing, anchor and micro-pile
Dynamic compaction
Soil stabilization, cold recycling of asphalt Tarshy
Earthworks
Production of asphalt, concrete and aggregates
Public
Projects
Highway and Bridge
Port, Coastal and Marine Structures
Dam and irrigation and drainage network
Construction of oil and gas and petrochemical facilities
Construction of water and sewer utilities
Soil improvement and ground reinforcement
Metro rail lines and structures
Industrial and special foundations, pile-situ
Soil stabilization, slope, digging trenches and walls
Residential, office and commercial
Partners
Contact Us
Job
Events
login
ورود همکاران
همکار گرامی لطفا سیستم مورد نظر را انتخاب نمایید
ورود
Link
ورود کارفرمایان
کارفرمای گرامی لطفا پروژه مورد نظر را انتخاب نمایید
ورود
Link
You are here :
Projects
/
View
اجرای شمع های درجا در نیروگاه سیکل ترکیبی گناوه
Start Date :
2010/02/20
ADDRESS :
گناوه ایران
Employer :
مپنا 3
End Date :
2011/03/07
Execution Time :
3 ماه
Consultant :
مپنا 3
Index values project
تخریب بتن: 233مترمکعب
پی کنی:7024 مترمکعب
حفاری:231500 متر طول
اجرای شمعهای درجاریز پروژه نیروگاه کناوه به تعداد تقریبی 1500 حلقه